Manual Balance Tutorial

Top  Previous  Next

Tutorial Objective:

This tutorial section will show you how to create a manual line balance, and use the grouping and two sided balance features. Please use the sample scenario file Single Pumps.xml (located in the Help Directory of your CD, or available on the Proplanner website) for this tutorial.

 

 

Step 1:  Opening a scenario

 

 

I.Open the tutorial scenario file called “Single Pumps.xml”.  “File => Open Scenario”

 

II.For clearing the existing task station assignments, go to Balancing Station View and then select Balance => Clear All Assignments.

 

 

 

Figure 20:  Clear all assignments
Figure 20:  Clear all assignments

 

 

 

III.Next, go to File => Properties and change Line Side to Two Sided’.

 

 

Figure 21:  Change line side to two sided
Figure 21:  Change line side to two sided

 

 

 

Step 2:  Assigning Groups

 

 

I.Go to the Task Grouping tab in the Task Editor. Highlight activities 40S-001 and 40S-002, right click and select Add to Group…’.

 

 

 
Figure 22:  Add group
Figure 22:  Add group

 

 

II.Create a new task group U-Cup’.

 

 

Figure 23:  New group named U-cup
Figure 23:  New group named U-cup

 

 

 

III.A new group by the name is added U-Cup is added. 

 

 

 

Figure 24:  Grouped tasks
Figure 24:  Grouped tasks
 

 

  

Step 3:  Assigning line sides

 

 

I.Go to the Task Sheet tab and assign Line Side. Change line side of 40S-001 and 40S-002 to R.

 

 

Figure 25:  Change line side for two tasks
Figure 25:  Change line side for two tasks

 

 

 

 

II.Similarly make the task PP01S-5 a right side task too.

               Note:  E means Either side and the task can be assigned the left or right side station.

 

 

Step 4:  Manually balancing

 

 

I.Go to Balancing Station View. (View = > Balancing Station View) and open the Unassigned Processes window on the left.
       Hint: You can anchor the Unassigned Processes by clicking on the top-right button and select it again to close it.

 

II.Assign a TAKT time (Edit => TAKT Time) and change it to 50, which essentially serve as a marker in the graph and for reporting purposes.

 

III.Select tasks 1 through 5 in the Unassigned Processes’ list, right click and assign to station BB001. An error is shown that a right side activity cannot be assigned to the left hand side station. Note that all the stations are left hand side stations.

 

IV.Go to the station editor and change station BB002 to right side and go back to the Balancing Station View’.

 

V.Now assign activity 5 & 6 (PP01S-5 & 40S-001) to station BB002. While doing so, task #7 (40S-002) will also be assigned to station BB002 as they belong to the same group.

 

VI.Complete assignment of the remaining tasks manually. You can generate the reports by clicking on the Report menu and selecting the appropriate menu.

 

Note: You could also automatically assign all of the tasks to stations and then manually change the assignments of selected tasks. Remember that if you move a task that is a member of a group, the entire group of tasks will be moved.