Reassign Work |
Top Previous Next |
|
Once the auto balance has been completed you can further fine tune the balance by manually moving work to different stations. To accomplish this, Right click on the tasks to be moved, select the 'Change Assignment' option. Next, select the station and/or operator to which the task should be assigned to (Figure 1). Rebalancing the line again through the 'Auto Balance' option will bring back the original balance.
|