mBOM Authoring Options for an Operation
 Figure 1: mBOM authoring options with an operation selected |
Header Tab
| • | Allows users to edit Name, Description, Quantity, and Effectivity dates. |
| • | Users can also select the line side of the activity as Left, Right, or Either. |
| • | The user can map a Boundary to an operation. This can be done by clicking on the Attach button. A form with the a list of plants and their corresponding boundaries will show up. The user then just needs to select the required boundary. |
Time Tab
| • | The Time tab displays the different times for each activity under the selected operation. |
| • | The Time tab provides information about Observed Time, Calculated Time, Estimated Time, Set up Time, % Value addition & frequency. |
| • | The user can only specify Estimated Time and Set up Time, the other two are calculated through specific controls. |
| • | The user can specify the frequency per cycle of an activity along with the percentage of value addition. |
| • | The “RollUp Type” should be set on Graph for most calculations. A detailed explanation of the same is discussed in the activities section. |
Gantt Chart Editor Tab
| • | The Gantt chart editor is used to specify the sequence in which the activities are to be performed. |
| • | By clicking the default button activities are arranged in sequence. |
| • | The sequence can be altered by changing the values of ‘From Node’, ‘To Node’, Delay Type, Delay Time, Add Arc & Delete Arc. |
E.g. in the Gantt chart below, the sequence of activities is:
 Figure 2: Gantt Chart |
 Figure 3: Precedence diagram 1 |
In order to define activity A2 parallel to A3, the user would have to delete arc A2 to A3 and add an arc from A1 to A3.
 Figure 4: Precedence diagram 2 |
| a) | Click on the arc A2 to A3. |
| b) | Click on the Delete Arc button. |
| c) | Select activity A1 form the “From Node” drop down menu and activity A3 from the “To Node” drop down. |
| d) | The Arcs list would now have changed. |
 Figure 5: Task list |
The Gantt chart below now shows the two activities in parallel.
 Figure 6: Gantt chart with activities in parallel |
History Tab
| • | The history tracking feature allows the user to enter details about changes made to the process and maintain a log of all changes and modifications made to the process. |
|